Segment akhir jalan berkembar Bukit Kukus akan siap Julai 2020: Exco Jagdeep

Final MBPP segment of Bukit Kukus Paired Road project at 78% progress and due to be completed in July 2020.

Thousands of road users to benefit by Bukit Kukus Paired Road project by July 2020.Final MBPP segment of Bukit Kukus Paired Road project at 78% progress and due to be completed in July 2020.Conducting a spot check on the 1.6 km third segment of the Bukit Kukus paired road project, which will be connected to Jalan Tun Sardon. The 3 segments of this biggest project ever undertaken by MBPP, costs RM370.1 million and is expected to be completed in July 2020.It is hoped MBPP will complete the project on time so that thousands of road users can benefit from it, and also so as to alleviate traffic congestion in that area.Beribu-ribu pengguna jalan raya akan dimanfaatkan oleh pembangunan projek Jalan Berkembar Jalan Bukit Kukus menjelang Julai 2020.Segmen terakhir MBPP Projek Jalan Berkembar Jalan Bukit Kukus pada tahap kemajuan 78% dan akan siap pada Julai 2020.Menjalankan pemeriksaan di segmen ketiga Jalan Bukit Kukus sepanjang 1.6km, yang akan berhubung dengan Jalan Tun Sardon.Projek terbesar yang pernah dilaksanakan oleh MBPP ini merangkumi 3 segmen, berharga sebanyak RM370.1 juta dan dijangka siap pada Julai 2020.Diharapkan MBPP akan siapkan bahagian mereka di projek tersebut mengikut jadual untuk manfaat beribu-ribu pengguna jalan raya dan untuk menyelesaikan masalah kesesakan lalu lintas di kawasan ini.成千上万的道路使用者将在明年7月从米桶山路项目受益。MBPP米桶山路项目的最后阶段已完成78%,预计将于明年7月完工。对米桶山路的第三阶段进行检查,该段将与Jalan Tun Sardon相连,长约1.6公里。这3段路是MBPP有史以来最大的项目,总投资了RM370.1百万,预计将于明年7月完工。希望MBPP能够按时完成项目,以便成千上万的道路使用者可以从中受益,可以缓解该地区的交通拥堵的情况。

Posted by Jagdeep Singh Deo 'Serving the People' on Wednesday, 7 August 2019

Exco Perumahan, Kerajaan Tempatan dan Perancangan Bandar & Desa, Sdr Jagdeep Singh Deo:

Beribu-ribu pengguna jalan raya akan dimanfaatkan oleh pembangunan projek Jalan Berkembar Jalan Bukit Kukus menjelang Julai 2020.

Segmen terakhir MBPP Projek Jalan Berkembar Jalan Bukit Kukus pada tahap kemajuan 78% dan akan siap pada Julai 2020.

Menjalankan pemeriksaan di segmen ketiga Jalan Bukit Kukus sepanjang 1.6km, yang akan berhubung dengan Jalan Tun Sardon.

Projek terbesar yang pernah dilaksanakan oleh MBPP ini merangkumi 3 segmen, berharga sebanyak RM370.1 juta dan dijangka siap pada Julai 2020.

Diharapkan MBPP akan siapkan bahagian mereka di projek tersebut mengikut jadual untuk manfaat beribu-ribu pengguna jalan raya dan untuk menyelesaikan masalah kesesakan lalu lintas di kawasan ini.

成千上万的道路使用者将在明年7月从米桶山路项目受益。

MBPP米桶山路项目的最后阶段已完成78%,预计将于明年7月完工。

对米桶山路的第三阶段进行检查,该段将与Jalan Tun Sardon相连,长约1.6公里。

这3段路是MBPP有史以来最大的项目,总投资了RM370.1百万,预计将于明年7月完工。

希望MBPP能够按时完成项目,以便成千上万的道路使用者可以从中受益,可以缓解该地区的交通拥堵的情况。

Thousands of road users to benefit by Bukit Kukus Paired Road project by July 2020.

Final MBPP segment of Bukit Kukus Paired Road project at 78% progress and due to be completed in July 2020.

Conducting a spot check on the 1.6 km third segment of the Bukit Kukus paired road project, which will be connected to Jalan Tun Sardon.

The 3 segments of this biggest project ever undertaken by MBPP, costs RM370.1 million and is expected to be completed in July 2020.

It is hoped MBPP will complete the project on time so that thousands of road users can benefit from it, and also so as to alleviate traffic congestion in that area.


Jalan Berkembar Bukit Kukus jangka siap Julai 2020 – Exco

Projek pembinaan Jalan Berkembar Bukit Kukus kini telah mencapai pemajuan sebanyak 78 peratus dengan jangkaan siap Julai 2020.

Exco Perumahan, Kerajaan Tempatan dan Perancangan Bandar & Desa, Sdr Jagdeep Singh Deo berkata, pembangunan jalan berkembar tersebut merupakan projek terbesar yang pernah dibangunkan MBPP untuk kemudahan orang ramai dengan kos keseluruhan bernilai lebih RM371 juta.

Jelasnya, kos pembinaan jalan berkembar berkaitan menelan belanja sebanyak RM275,600,000, itu tidak termasuk dengan kos pengambilan tanah (RM83,509,670.50) dan khidmat perunding (RM11,000,000).

“Sejak projek ini dimulakan (2016) sehingga tahun 2018 sebanyak RM275,804,433 telah dibelanjakan oleh MBPP untuk pembinaan projek ini termasuk kos pengambilan tanah.

“Pada tahun ini, Majlis telah memperuntukkan sebanyak RM44,200,000 dan untuk tahun 2020 (RM37,355,000) lagi untuk pembinaan Jalan Berkembar Jalan Paya Terubong ini,” ujarnya sambil memaklumkan bahawa kos projek berkenaan menelan hampir 40 peratus daripada kos perbelanjaan MBPP.

Artiket penuh pada Buletin Mutiara:


Bukit Kukus paired road project partly open for traffic August next year

Motorists, especially those from Paya Terubong and Air Itam, will have an alternative road to travel once a section of the Bukit Kukus paired road project is open to the public next year.

State Public Works, Utilities and Flood Mitigation Committee chairman Sdr Zairil Khir Johari said the three segments (2.8km) undertaken by Penang Island City Council (MBPP) are scheduled complete in July next year, hence, it should be open in August next year.

“The other segments undertaken by Geo Valley Sdn Bhd (800m) and PLB Land Sdn Bhd (1.4km) are scheduled to complete in a few years.

“Aspen Group has taken over the segment contracted to Geo Valley Sdn Bhd,” he told a press conference after a site visit in Lebuh Bukit Jambul today.

Full article on Buletin Mutiara: